Related Permit Details
Application/Permit Information
Application/Permit Number:
Application Type:
Application Date:
Status:
Project Name:
Project Description:
Type | Status | Outcome | Cost | Date | Inspector | Checklist | Inspector Notes | General Notes |
---|---|---|---|---|---|---|---|---|
Mechanical - Rough In | Passed | Approved | April 19, 2021 12:00 AM | Robert King | Section A level 1 OK to sheetrock 10 apartments and Corridor. Corridor duct complete on 1st floor. | |||
Mechanical - Rough In | Passed | Approved | April 13, 2021 12:00 AM | Robert King | Section A level 4 OK to sheetrock. 10 apartments and partial corridor. Duct in corridor not completeat end that connects to section B. Section A level 3 OK to insulte dryer ducts | |||
Mechanical - Rough In | Passed | Approved | April 14, 2021 12:00 AM | Robert King | Section 3 level 3 OK to sheetrock 10 apartments and partial corridor. Duct not complete at end of corridor that connects to section B. Ok to wraop dryer ducts Area A leves 1 & 2 | |||
Mechanical - Above Ceiling | Passed | Approved | May 14, 2021 12:24 PM | Robert King | Section B level 2 & 3 Ok to sheetrock apartments and corridor Section B level 4 Ok to insulate dryer and fresh air ducts | |||
Mechanical - Rough In | Passed | Approved | April 12, 2021 12:00 AM | Robert King | Section A level 4 10 apartments Rough in Good. need to see fire wrap before shetrock | |||
Mechanical - Rough In | Passed | Approved | April 15, 2021 12:00 AM | Robert King | Section A level 2 OK to sheetrock. 10 apartments and corridor to end near area B | |||
Mechanical - Final | Passed | Approved | September 24, 2021 11:31 AM | James Hobby | level 4 final | |||
Mechanical - Above Ceiling | Passed | Approved | May 20, 2021 11:36 AM | Robert King | Level 1 amenity area. OK to insualte fresh air intake ducts | |||
Mechanical - Final | Passed | Approved for Occupancy | November 30, 2021 8:30 AM | James Hobby | ||||
Mechanical - Duct Seal | Available | |||||||
Mechanical - Rough In | Passed | Approved | May 13, 2021 12:00 AM | Robert King | Section B Level 2 & 3. Ok to insulate dryer vents and fresh air ducts. Section B level 1 Ok to install fire rated sheetrock ceiling in amenities room. | |||
Mechanical - Above Ceiling | Passed | Approved | May 18, 2021 10:47 AM | Robert King | Section B level 4 OK to sheetrock apartments and corridor | |||
Mechanical - Above Ceiling | Passed | Approved | May 27, 2021 11:48 AM | Robert King | Level 1 Amenity area OK to sheetrock | |||
Mechanical - Above Ceiling | Passed | Approved | June 7, 2021 12:00 AM | James Hobby | Level 2 Amenity area OK to sheetrock | |||
Mechanical - Final | Passed | Approved | October 1, 2021 1:35 PM | James Hobby | level 3 final | |||
Mechanical - Final | Canceled | Not Applicable | October 6, 2021 10:05 AM | James Hobby | per contractor | |||
Mechanical - Final | Passed | Approved | October 7, 2021 9:43 AM | James Hobby | Level 1 and 2 final. Note: this is for apartment units only. | |||
Mechanical - Final | Canceled | Not Applicable | October 11, 2021 12:23 PM | Robert King | Per Larry Conner | |||
Mechanical - Final | Passed | Approved | October 12, 2021 10:22 AM | James Hobby | Outside and amenity area. |