Partial Occupancy - Building |
Passed |
Approved for Occupancy |
|
April 24, 2020 3:57 PM |
Wyatt Blalock |
|
COVID-19 emergency contingency plan ( L1 and 2 ) conditionally approved see FMO notes. |
|
Partial Occupancy - Electrical |
Passed |
Approved for Occupancy |
|
April 17, 2020 9:48 AM |
Ron Watson |
|
level 1 and 2 only |
|
Partial Occupancy - Plumbing |
Passed |
Approved for Occupancy |
|
April 16, 2020 10:38 AM |
Chris Clark |
|
First and second floor only |
|
Partial Occupancy - Mechanical |
Passed |
Approved for Occupancy |
|
April 17, 2020 7:44 AM |
Gary Wheeler |
|
|
|
Partial Occupancy - Fire Prevention |
Passed |
Approved for Occupancy |
|
April 24, 2020 3:57 PM |
Jody Morton |
|
Entry by WCB authority FM JM 1) A sealed letter from the design engineer of record (Mr. Torres) confirming that the design and operation of the fire and smoke dampers are in accordance with all applicable building, fire, and mechanical codes. 2) Evacuation plans shall be posted in accordance with the NC Fire Code, 2018 Edition throughout the occupied areas in compliance with Institutional Occupancy requirements. 3) A fire watch plan must be submitted to our office for review and approval prior to partial occupancy for Floors 1 and 2.
|
|
Partial Occupancy - Cross Connection |
Passed |
Approved for Occupancy |
|
April 21, 2020 12:00 AM |
Tony Pickett |
|
Levels 1 & 2 only. |
|