BUILDING - Insulation |
Passed |
Approved |
|
May 14, 2020 3:29 PM |
Adrienne Harrington |
|
Level P1: Elevator machine room insulation: Batts in Walls |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
July 1, 2021 11:46 AM |
Steve Crist |
|
Rated walls in CATH 1 Room 01B46 , Cath 2 Room 01B42, Procedure room 01B48 |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
June 18, 2020 3:49 PM |
Karey McConnell |
|
Above Ceiling Partial Approved Level 10 A Hard Ceiling Corridors 3A, 10B49X and 10A00V |
|
BUILDING - Framing |
Passed |
Approved |
|
January 30, 2019 11:38 AM |
Todd Miller |
|
Shaft walls at levels 1 and 2 - B area at L5 - North face, A area at L7-8, North face |
|
BUILDING - Insulation |
Passed |
Approved |
|
June 4, 2019 11:43 AM |
Julian Arroyo |
|
Edge of slab west col. line P 1-11 level 02 - penthouse |
|
BUILDING - Final |
Canceled |
Not Applicable |
|
April 9, 2020 12:00 AM |
Randall Stewart |
|
spoke with super to discuss the need for a Partial Occupancy permit in order to inspect for occupancy of these floors. |
|
BUILDING - Spot Check |
|
Not Applicable |
|
December 5, 2019 9:22 AM |
Randall Stewart |
|
approved temporary life safety plans for existing hospital are attached and as discussed with Architects of Record. |
|
BUILDING - Other |
Passed |
Approved |
|
April 15, 2019 3:10 PM |
Adrienne Harrington |
|
Slab Edge firestopping and firecaulk at precast panels on Level 1 |
|
BUILDING - Final/Multi-Family |
Available |
|
|
|
|
|
|
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
September 12, 2019 9:15 AM |
Steve Crist |
|
level 1, above hard ceilings, col line 4-11 between col C28-E |
|
BUILDING - Stocking |
Available |
|
|
|
|
|
|
|
BUILDING - Framing |
Passed |
Approved |
|
April 8, 2019 10:49 AM |
Steve Crist |
|
1) Level 00 electrical room A side and north wall 2) A side duct shaft level00 3) North wall IT room level 1 4) South wall V shaft east shaft level 1 5) V shaft level 2 wall |
|
BUILDING - Other |
Passed |
Approved |
|
April 22, 2019 8:35 AM |
Julian Arroyo |
|
1st Floor Edge of slab fireproofing ffron column lin 2-14 on the north side and AA-FF on west side and from 14-11 on the south side |
|
BUILDING - Framing |
Passed |
Approved |
|
April 25, 2019 2:45 PM |
Adrienne Harrington |
|
Level 0T - North Wall of Duct Shaft 6164. (not a rated wall) --Edge of slab fire stopping at West wall of the loading dock and adjacent Southwest Precast wall |
|
BUILDING - Other |
Failed |
Disapproved |
|
April 26, 2019 12:00 AM |
Adrienne Harrington |
|
Slab edge firestopping to precast west Levels 0T,2,3,4,6,8 were complete --1) Slab edge firestopping to precast west Levels 7 and 9 were incomplete |
|
BUILDING - Other |
Passed |
Approved |
|
May 6, 2019 2:04 PM |
Adrienne Harrington |
|
Slab edge firestopping roof partial for West/Northwest/Southwest parapit walls and Precast on the West side -- NOTE: Corners not Inspecterd, Contractor waiting on higher-gauge steer for completion |
|
BUILDING - Framing |
Passed |
Approved |
|
May 2, 2019 3:33 PM |
Steve Crist |
|
Shaftliner in shaft walls at the following: 3rd fl southside 6 line D-E, 2nd fl south side 6 line D-E, North side 8 line A-B, 1st fl south side 11 line GT-JJ |
|
BUILDING - Framing |
Passed |
Approved |
|
May 9, 2019 3:14 PM |
Michael Glass |
|
Levels: 0 Basement, 00, 3rd, 4th, 6th North Vertical Plenum wall framing |
|
BUILDING - Other |
Passed |
Approved |
|
May 16, 2019 2:56 PM |
Steve Crist |
|
remainder of Roof Slab Edge Fire Stop- North, South and East.
|
|
BUILDING - Other |
Passed |
Approved |
|
May 20, 2019 1:27 PM |
Steve Crist |
|
Partial slab edge fire stop floors 3, 4, 6 northwest, north, south walls less 3 bays on floor 3, 5 bays on floor 4, and 4 bays on floor 6 |
|
BUILDING - Framing |
Passed |
Approved |
|
May 21, 2019 1:42 PM |
Todd Miller |
|
Metal Stud framing in Rooms; 0068ER, 0068ER, 00A44ER, 0087ER, and 00A43TC |
|
BUILDING - Framing |
Passed |
Approved |
|
May 23, 2019 2:19 PM |
Adrienne Harrington |
|
North Plenum Wall Level 0B and 00 and South Wall of E-Sub Station Room 00A45ER. |
|
BUILDING - Framing |
Passed |
Approved |
|
May 31, 2019 3:13 PM |
Karey McConnell |
|
Wall Framing Approved. 3 metal Stud Walls. Level 00 in rooms 00A41ER and P-Tube 00B51. |
|
BUILDING - Framing |
Passed |
Approved |
|
June 4, 2019 11:43 AM |
Julian Arroyo |
|
South Plenum wall Framing inspection on Level 00.
|
|
BUILDING - Framing |
Passed |
Approved |
|
June 5, 2019 1:48 PM |
Todd Miller |
|
Partial for vertical plenum levels 07 thru 11 north/northwest side. |
|
BUILDING - Other |
Passed |
Approved |
|
June 11, 2019 2:10 PM |
Julian Arroyo |
|
Firestopping 3rd floor south southwest and west edge of slab 4 th floor southwest and west and 6th floor southwest and west also loading dock top of wall |
|
BUILDING - Framing |
Canceled |
Not Applicable |
|
June 19, 2019 12:00 AM |
Todd Miller |
|
|
|
BUILDING - Framing |
Failed |
Disapproved |
|
June 19, 2019 8:54 AM |
Steve Crist |
|
electrical rooms floors 9,10,11 fire caulk behind beam above wall plate all 6 rooms |
|
BUILDING - Framing |
Canceled |
Not Applicable |
|
June 27, 2019 3:04 PM |
Randall Stewart |
|
no inspection-could not reach on site personnel (left vm) |
|
BUILDING - Other |
Canceled |
Not Applicable |
|
June 20, 2019 12:00 AM |
Todd Miller |
|
|
|
BUILDING - Other |
Canceled |
Not Applicable |
|
June 27, 2019 3:04 PM |
Randall Stewart |
|
no inspection-could not reach on site personnel (left vm) |
|
BUILDING - Framing |
Passed |
Approved |
|
July 1, 2019 10:05 AM |
Adrienne Harrington |
|
Framing Electrical Rooms on levels 9, 10 and 11 -- Fire Stopping South Plenum Level 0B, 00 and 0T. |
|
BUILDING - Framing |
Failed |
Disapproved |
|
July 5, 2019 8:47 AM |
Karey McConnell |
|
Framing Disapproved. No inspection. Called names from previous inspection Lynn and Andy and had no response. Please reschedule and include numbers to responsible personnel. |
|
BUILDING - Framing |
Passed |
Approved |
|
July 9, 2019 1:40 PM |
Julian Arroyo |
|
Level 00/0T North plenum fire stopping. Level 00 P-Tube Room Framing |
|
BUILDING - Other |
Passed |
Approved |
|
July 8, 2019 1:21 PM |
Julian Arroyo |
|
North side remainder 2nd 3rd and 4th floor also interior insulation and water test 2nd 3rd and 4th |
|
BUILDING - Framing |
Passed |
Approved |
|
July 9, 2019 1:40 PM |
Julian Arroyo |
|
Level 1 Pre-drywall framing inspection 01A01-01A17and Team Station |
|
BUILDING - Framing |
Passed |
Approved |
|
July 17, 2019 2:11 PM |
Randall Stewart |
|
plenum framing and pump room wallframing |
|
BUILDING - Insulation |
Passed |
Approved |
|
July 19, 2019 2:18 PM |
Adrienne Harrington |
|
North and South Plenum ceiling |
|
BUILDING - Framing |
Passed |
Approved |
|
July 25, 2019 11:12 AM |
Steve Crist |
|
OT level south wall shaft east end, north wall east of stair 3, level 00: normal substation roomcolumn wraps, med gas room column wrap and west wall, south shaft wall |
|
BUILDING - Insulation |
Passed |
Approved |
|
July 30, 2019 4:15 PM |
Adrienne Harrington |
|
Center Core and West Core framed walls on the roof |
|
BUILDING - Framing |
Passed |
Approved |
|
August 5, 2019 2:51 PM |
Todd Miller |
|
Duke BTA Level 1B and Level 2A Framing for drywall hang |
|
BUILDING - Insulation |
Canceled |
Not Applicable |
|
August 5, 2019 12:00 AM |
Todd Miller |
|
|
|
BUILDING - Other |
Passed |
Approved |
|
August 9, 2019 1:56 PM |
Steve Crist |
|
slab edge fire safing at waiting room south 2) Wing wall south west facade lower half framing mounted on welded steel brackets |
|
BUILDING - Other |
Passed |
Approved |
|
August 13, 2019 9:03 AM |
Steve Crist |
|
slab edge insulation west side 7, 8, 9, 10, 11 south east corner 2, 3, 4, 6, 7, 8, 9, 10 |
|
BUILDING - Insulation |
Passed |
Approved |
|
August 20, 2019 9:45 AM |
Julian Arroyo |
|
Slab edge Lvl 02 firestop and insulation -excluding elevator lobby and buck-hoist areas |
|
BUILDING - Insulation |
Canceled |
Not Applicable |
|
August 22, 2019 12:00 AM |
Todd Miller |
|
|
|
BUILDING - Framing |
Passed |
Approved |
|
August 23, 2019 2:32 PM |
Michael Glass |
|
Section 2B |
|
BUILDING - Framing |
Passed |
Approved |
|
August 27, 2019 4:39 PM |
Adrienne Harrington |
|
Level 00: East Wall of MV Switchgear Room -- Level 0T: Edge of slab firestop |
|
BUILDING - Insulation |
Passed |
Approved |
|
September 3, 2019 2:20 PM |
Michael Glass |
|
Insulation and Fire stop at floor 7th and 8th Floors, Fire Stop at floor 9th Floor; Areas--South, Southwest, North, Northwest, and West |
|
BUILDING - Framing |
Passed |
Approved |
|
September 5, 2019 8:22 AM |
Todd Miller |
|
Slab edge firestop - 2B |
|
BUILDING - Framing |
Passed |
Approved |
|
September 5, 2019 8:22 AM |
Todd Miller |
|
Interior partitions 3A and 3B |
|
BUILDING - Framing |
Passed |
Approved |
|
September 12, 2019 9:15 AM |
Steve Crist |
|
Level 4B east end wall and hard ceiling framing, Level 2A rooms 02A-16, 17 Hard ceiling framing |
|
BUILDING - Insulation |
Passed |
Approved |
|
September 12, 2019 9:15 AM |
Steve Crist |
|
Exter firestop insulation levels 3, 4, 6 SW corner |
|
BUILDING - Framing |
Canceled |
Not Applicable |
|
September 18, 2019 12:00 AM |
Adrienne Harrington |
|
Contractor texted to cancel |
|
BUILDING - Insulation |
Passed |
Approved |
|
September 24, 2019 3:37 PM |
Michael Glass |
|
Complete UL assembly with Fire caulk Level 3 waiting Rm, level 3, 4, & 6 NE wall, Level 6 SE wall, Level 4 waiting Rm, 7 areas total |
|
BUILDING - Framing |
Passed |
Approved |
|
October 4, 2019 4:07 PM |
Adrienne Harrington |
|
Pre-Rock framing Duke BTA Levels 4A and 6B |
|
BUILDING - Insulation |
Passed |
Approved |
|
October 4, 2019 4:07 PM |
Adrienne Harrington |
|
Slab edge firestop at curtain wall levels 10 and 11 North and South elevations |
|
BUILDING - Framing |
Passed |
Approved |
|
October 10, 2019 2:08 PM |
Adrienne Harrington |
|
Level 1 Ramp Hard Ceiling Framing |
|
BUILDING - Insulation |
Passed |
Approved |
|
October 16, 2019 12:22 PM |
Adrienne Harrington |
|
Slab edge firestop at curtain wall levels 10 and 11 West and Southwest elevations |
|
BUILDING - Insulation |
Passed |
Approved |
|
October 23, 2019 2:37 PM |
Steve Crist |
|
West roof edges, fire seal at bottom of parapet that could not be finished before due to structural restrictions |
|
BUILDING - Insulation |
Failed |
Disapproved |
|
October 29, 2019 2:15 PM |
Julian Arroyo |
|
Firestop spray at edge of slab level 10 severals areas are not ready need to complete and call for reinspection |
|
BUILDING - Framing |
Passed |
Approved |
|
October 29, 2019 12:25 PM |
Adrienne Harrington |
|
Section 6A Framing -- Section 4A Patient/Isolation Rooms Hard Ceilings -- Section 4A Alcove Soffits |
|
BUILDING - Insulation |
Passed |
Approved |
|
November 7, 2019 9:20 AM |
Todd Miller |
|
Curtainwall edge of slab firestop roof level. Red fire caulk/spray levels 7-9 |
|
BUILDING - Framing |
Passed |
Approved |
|
November 20, 2019 12:11 PM |
Adrienne Harrington |
|
Hard Ceiling Framing ISO Rooms Level 3 -- Level 8 Full Framing |
|
BUILDING - Insulation |
Passed |
Approved |
|
November 21, 2019 10:00 AM |
Steve Crist |
|
Remainder slab edge sections sealing floors 2 through 11 |
|
BUILDING - Insulation |
Passed |
Approved |
|
December 3, 2019 1:23 PM |
Todd Miller |
|
Remainder of red firestop spray at levels 10 and 11 bottom track exterior walls |
|
BUILDING - Framing |
Passed |
Approved |
|
December 17, 2019 2:32 PM |
Michael Glass |
|
Interior Walls Section 9B |
|
BUILDING - Insulation |
Passed |
Approved |
|
December 31, 2019 12:55 PM |
Adrienne Harrington |
|
Levels 2-7: Exterior wall Batt insulation at the slide-out Preston loading decks |
|
BUILDING - Framing |
Passed |
Approved |
|
January 3, 2020 3:43 PM |
Adrienne Harrington |
|
Level 7 Hard Ceiling Framing ISO Rooms and recessed areas at hallways |
|
BUILDING - Insulation |
Passed |
Approved |
|
January 9, 2020 8:15 AM |
Todd Miller |
|
Red firespray @ bottom track levels 2-9 where the slide out material decks were. North elevation west end. |
|
BUILDING - Framing |
Passed |
Approved |
|
January 17, 2020 2:04 PM |
Todd Miller |
|
Levels 3 and 7 Waiting Area Hard Ceiling Inspection, Level 0T East Plenum Wall, |
|
BUILDING - Framing |
Passed |
Approved |
|
January 22, 2020 12:13 PM |
Adrienne Harrington |
|
Pre-Rock Level 9A |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
January 29, 2020 4:55 PM |
Adrienne Harrington |
|
Level 2 Mockup Room 02A02 |
|
BUILDING - Framing |
Passed |
Approved |
|
January 29, 2020 4:50 PM |
Adrienne Harrington |
|
Level 10 A & B: Interior Walls |
|
BUILDING - Framing |
Passed |
Approved |
|
January 29, 2020 4:58 PM |
Adrienne Harrington |
|
Level 4A BMT Rooms and recessed areas at hallways Hard Ceiling Framing |
|
BUILDING - Insulation |
Passed |
Approved |
|
February 11, 2020 10:04 AM |
Julian Arroyo |
|
North East exterior wall batt insulation Column 2 - Column 1 levels 1-11. |
|
BUILDING - Framing |
Failed |
Disapproved |
|
February 14, 2020 1:49 PM |
Peter Gervais |
|
All fire rated wall, shafts and floor pentration shouls be completed before check for framing of a complete floor |
|
BUILDING - Framing |
Passed |
Approved |
|
February 20, 2020 2:01 PM |
Todd Miller |
|
Waiting area ceiling framing levels 2 thru 10. |
|
BUILDING - Insulation |
Passed |
Approved |
|
February 18, 2020 9:03 AM |
Peter Gervais |
|
Levels 10 and 11 exterior insulation north side, loading platform |
|
BUILDING - Framing |
Passed |
Approved |
|
February 20, 2020 2:01 PM |
Todd Miller |
|
11th floor area B - interior partitions and soffits |
|
BUILDING - Framing |
Passed |
Approved |
|
March 12, 2020 12:00 AM |
Peter Gervais |
|
performed a site visit as requested to inspect 10A90, 10A17,10A84 NOTE: entry by RS due to malware attack |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
March 19, 2020 12:00 AM |
Todd Miller |
|
Approved per conversation with TM
Results entered by PG on 3/20/20 for TM due to Malware attack.
|
|
BUILDING - Framing |
Passed |
Approved |
|
March 16, 2020 12:00 AM |
Peter Gervais |
|
10th Floor entry by RS due to malware attack.
|
|
BUILDING - Framing |
Passed |
Approved |
|
March 20, 2020 12:00 AM |
Todd Miller |
|
AP all of the following: 1) section 11A 2) Stair shaft 2 floors 12-0B and adjacent elevator lobbies 3) marriage wall between old and new construction at concourses on floors 1 and 2 4) stair shaft 1 floors 1-3 5) bathrooms 54T, floors 1-3 and 56T floor 1
NOTE: entry by RS due to malware attack |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
March 24, 2020 2:55 PM |
Steve Crist |
|
2hr, 1hr, smoke walls 2nd floor area to turned over. |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
April 3, 2020 7:56 AM |
Todd Miller |
|
Level 4A Patient Rooms. |
|
BUILDING - Framing |
Passed |
Approved |
|
April 28, 2020 1:16 PM |
Adrienne Harrington |
|
Level 3/4/6/7/8 Concourse |
|
BUILDING - Framing |
Passed |
Approved |
|
April 28, 2020 1:15 PM |
Adrienne Harrington |
|
Levels 4-11 Stairs |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
May 7, 2020 8:02 AM |
Steve Crist |
|
Above ceiling 7th floor room 16, 17, NW corridor end, T1-T2 lobby,Norish room by 76. |
|
BUILDING - Framing |
Passed |
Approved |
|
May 14, 2020 3:29 PM |
Adrienne Harrington |
|
Level P1: Elevator machine room framing |
|
BUILDING - Insulation |
Passed |
Approved |
|
May 14, 2020 3:29 PM |
Adrienne Harrington |
|
Level 00 - West Side and South Side Exterior Walls: Batts in walls |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
May 18, 2020 4:22 PM |
Adrienne Harrington |
|
Level 8 Hard Ceilings: Isolation Rooms / Corridor Sections |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
May 18, 2020 4:23 PM |
Adrienne Harrington |
|
Level 3 Above Ceiling: All Fire-Rated Walls (Contractor made corrections during inspection - Re-checked after full inspection completed) -- Trade/Equipment Roomw / Corridors / Shafts / 37 ICU Rooms / Stations / All Other Rooms |
|
BUILDING - Framing |
Passed |
Approved |
|
May 21, 2020 3:05 PM |
Adrienne Harrington |
|
Level P1 - Walls / Elevator Machine Room (adjacent to stair 1) |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
June 3, 2020 11:51 AM |
Julian Arroyo |
|
Above Ceiling Approved Hard Ceiling 9th floor |
|
BUILDING - Insulation |
Passed |
Not Applicable |
|
June 12, 2020 1:04 PM |
Karey McConnell |
|
Partial Insulation Approved Curtain Wall and Slab Edge South Buck Hoist 2-P1 |
|
BUILDING - Framing |
Passed |
Approved |
|
June 17, 2020 9:04 AM |
Todd Miller |
|
Shaft liner for rated walls in pharmacy on level 00 |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
June 18, 2020 3:49 PM |
Karey McConnell |
|
Above Ceiling Partial Approved Level 10 A Hard Ceiling Patient Rooms 1-17 |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
June 23, 2020 10:57 AM |
Steve Crist |
|
Above ceiling corridors and patient rooms and support rooms Level 4B. |
|
BUILDING - Final |
Passed |
Approved |
|
June 30, 2020 9:49 AM |
Todd Miller |
|
Partial - level 3 - see partial occupancy permit |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
July 8, 2020 9:07 AM |
Todd Miller |
|
Level 6 - all areas |
|
BUILDING - Above Ceiling |
Failed |
Disapproved |
|
July 31, 2020 12:08 PM |
Karey McConnell |
|
Above Ceiling Disapproved Level 7 B Side. 1) Area EVS - 07B71 Electrical work commencing. All others areas area approved. |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
July 31, 2020 12:07 PM |
Karey McConnell |
|
Above Ceiling Approved Level 7 A Side. |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
August 7, 2020 12:00 AM |
Peter Gervais |
|
waiting area level 2 - 3 |
|
BUILDING - Insulation |
Failed |
Disapproved |
|
August 7, 2020 12:00 AM |
Peter Gervais |
|
passed on floors 1, & 4 - 10, insulation still needed on floor 11 |
|
BUILDING - Slab |
Passed |
Approved |
|
August 7, 2020 2:43 PM |
Peter Gervais |
|
slab edge 4 -11 west buck host area |
|
BUILDING - Insulation |
Passed |
Approved |
|
September 10, 2020 9:26 AM |
Todd Miller |
|
Level 1 east elevator |
|
BUILDING - Framing |
Canceled |
Not Applicable |
|
August 17, 2020 12:00 AM |
Peter Gervais |
|
by request |
|
BUILDING - Framing |
Passed |
Approved |
|
August 18, 2020 2:57 PM |
Karey McConnell |
|
Framing Approved Level 00 Pharmacy |
|
BUILDING - Framing |
Passed |
Approved |
|
October 28, 2020 10:34 AM |
Todd Miller |
|
East elevators - floors 2-11 - secondary framing in elevator lobbies. |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
September 22, 2020 9:09 AM |
Julian Arroyo |
|
Above Ceiling inspection on level 9 excluding waiting area |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
September 24, 2020 10:38 AM |
Julian Arroyo |
|
Above Ceiling Approved for center core elevator lobby levels 2 and 3 |
|
BUILDING - Final |
Failed |
Disapproved |
|
October 1, 2020 8:24 AM |
Todd Miller |
|
Install permanent tactile signage at all stair access points and in stairwells of all occupied levels |
|
BUILDING - Final |
Passed |
Approved |
|
March 8, 2021 11:38 AM |
Todd Miller |
|
Final Inspection for Level 6 |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
October 6, 2020 3:12 PM |
Todd Miller |
|
Above Ceiling inspection at the waiting area for levels 4-7. |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
October 12, 2020 8:29 AM |
Todd Miller |
|
Level 8-9 waiting area above ceiling. |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
October 16, 2020 8:08 AM |
Julian Arroyo |
|
Above Ceiling Approved 10 floor Waiiting Area |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
October 27, 2020 11:52 AM |
Todd Miller |
|
Level 11 west conference room |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
November 24, 2020 1:11 PM |
Todd Miller |
|
Level 11 Above Ceiling. |
|
BUILDING - Framing |
Passed |
Approved |
|
November 24, 2020 1:11 PM |
Todd Miller |
|
DCT L00 Pharmacy Hard Ceiling Framing |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
December 3, 2020 12:27 PM |
Todd Miller |
|
Conference rooms, floors 4-11 |
|
BUILDING - Above Ceiling |
Failed |
Disapproved |
|
December 3, 2020 12:27 PM |
Todd Miller |
|
East elevator lobbies, both sides, floors 1-11 - Label, seal penetrations and seal tops of walls in the followinf - 03B60 - 09B95 - 10B65 - 11B65 - all others OK |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
December 8, 2020 11:35 AM |
Julian Arroyo |
|
Above Ceiling Elevator Lobbys Complete |
|
BUILDING - Framing |
Passed |
Approved |
|
December 23, 2020 9:21 AM |
Todd Miller |
|
Starbucks area |
|
BUILDING - Framing |
Passed |
Approved |
|
January 14, 2021 8:53 AM |
Todd Miller |
|
Framing Inspection for Starbucks Hard Ceiling as well as the High Concourse Hard Ceiling and Walls. |
|
BUILDING - Framing |
Passed |
Approved |
|
January 27, 2021 10:59 AM |
Steve Crist |
|
Soffit framing around piping ove loading dock. |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
February 10, 2021 2:33 PM |
Steve Crist |
|
Starbucks area storeroom , Concourse separation end wall |
|
BUILDING - Other |
Failed |
Disapproved |
|
March 2, 2021 10:57 AM |
Todd Miller |
|
Center core public elevator shafts - large gap in pit of west side shaft wall - East shaft OK |
|
BUILDING - Final |
Passed |
Approved |
|
April 8, 2021 2:02 PM |
Steve Crist |
|
Roof top deck, membrane and parapets and guards. |
|
BUILDING - Final |
Passed |
Approved |
|
March 16, 2021 3:31 PM |
Todd Miller |
|
Partial - Levels 7 and 8 |
|
BUILDING - Insulation |
Passed |
Approved |
|
March 16, 2021 3:38 PM |
Todd Miller |
|
Loading Dock ceiling - spray foam and itumescent coating |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
March 18, 2021 11:39 AM |
Todd Miller |
|
Level 00 at lay in ceiling areas except pharmacy |
|
BUILDING - Final |
Passed |
Approved |
|
March 19, 2021 10:12 AM |
Todd Miller |
|
Final Inspection for Level 9. |
|
BUILDING - Framing |
Canceled |
Not Applicable |
|
March 23, 2021 12:00 AM |
Todd Miller |
|
|
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
March 23, 2021 2:25 PM |
Todd Miller |
|
0T Level Elevator Lobby and room #0A92 on 00 Level. |
|
BUILDING - Final |
Passed |
Approved |
|
March 23, 2021 2:25 PM |
Todd Miller |
|
Level 11 Final Building Inspection. |
|
BUILDING - Framing |
Canceled |
Not Applicable |
|
March 26, 2021 12:00 AM |
Todd Miller |
|
|
|
BUILDING - Final |
Passed |
Approved |
|
March 30, 2021 12:58 PM |
Steve Crist |
|
Level 10 final building inspection |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
April 1, 2021 1:42 PM |
Todd Miller |
|
Above Ceiling Inspection for Level 1 Patient Transport Elevator Lobby |
|
BUILDING - Framing |
Passed |
Approved |
|
April 1, 2021 1:42 PM |
Todd Miller |
|
Level 1 Cath Lab Area |
|
BUILDING - Framing |
Passed |
Approved |
|
May 25, 2021 9:29 AM |
Todd Miller |
|
IT closet and electrical room knockout wall on L00 |
|
BUILDING - Framing |
Passed |
Approved |
|
July 1, 2021 11:46 AM |
Steve Crist |
|
Hard ceiling framing CATH 1 Room 01B46 , Cath 2 Room 01B42, Procedure room 01B48 |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
July 20, 2021 9:23 AM |
Todd Miller |
|
Level 1-B - Cath Lab Above Ceiling |
|
BUILDING - Final |
Passed |
Approved |
|
October 15, 2021 1:44 PM |
Todd Miller |
|
Partial - floors 4-0 - This completes all on-site inspections - Accessibility compliance and elevator equipment and shaft letters required for AO |
|
BUILDING - Final |
Passed |
Approved for Occupancy |
|
November 4, 2021 3:01 PM |
Todd Miller |
|
Received all final paperwork |
|
BUILDING - Framing |
Passed |
Approved |
|
February 1, 2022 10:06 AM |
Todd Miller |
|
Installation of smoke doors in public elevator lobbies required by DHSR |
|