BUILDING - Footing |
Available |
|
|
|
|
|
|
|
BUILDING - Foundation |
Available |
|
|
|
|
|
|
|
BUILDING - Slab |
Available |
|
|
|
|
|
|
|
BUILDING - Framing |
Passed |
Approved |
|
June 26, 2023 8:02 AM |
Shaun Liggett |
|
framing approved- partial framing rated walls observed one side drywal and light gauge framing |
|
BUILDING - Insulation |
Passed |
Approved |
|
June 30, 2023 10:11 AM |
Shaun Liggett |
|
insulation approved- batts in party wall |
|
BUILDING - Final |
Failed |
Disapproved |
|
August 4, 2023 10:48 AM |
Randall Stewart |
|
in vestibule (2 single doors have been changed to double doors) add approved hardware to these non rated exit doors from sanctuary. Also in vestibule exit sign on wrong side of wall to exit corridor on left side. all locations circled on jobsite copy |
|
BUILDING - Spot Check |
Available |
|
|
|
|
|
|
|
BUILDING - Other |
Available |
|
|
|
|
|
|
|
BUILDING - Angle |
Available |
|
|
|
|
|
|
|
BUILDING - Final/Multi-Family |
Available |
|
|
|
|
|
|
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
July 19, 2023 10:28 AM |
Julian Arroyo |
|
Above Ceiling Approved fire caulking -note you need to label all walls with fire rating can observe at the final |
|
BUILDING - Stocking |
Available |
|
|
|
|
|
|
|
BUILDING - Framing |
Passed |
Approved |
|
July 6, 2023 9:13 AM |
Shaun Liggett |
|
framing approved- partial singe layer on party walls ok to proceed to final layer drywall and sealant |
|
BUILDING - Final |
Passed |
Approved for Occupancy |
|
October 2, 2023 3:01 PM |
Shaun Liggett |
|
|
|