| BUILDING - Footing |
Available |
|
|
|
|
|
|
|
| BUILDING - Foundation |
Available |
|
|
|
|
|
|
|
| BUILDING - Slab |
Available |
|
|
|
|
|
|
|
| BUILDING - Framing |
Failed |
Disapproved |
|
January 5, 2023 7:55 AM |
Julian Arroyo |
|
Framing Disapproved as of July 2022 all MEP rough-in inspection must be passed proir to the framing inspection |
|
| BUILDING - Insulation |
Failed |
Disapproved |
|
January 25, 2023 12:15 PM |
Julian Arroyo |
|
Batt Insulation Disapproved Framing needs to passed proir to the insulation |
|
| BUILDING - Final |
Failed |
Disapproved |
|
January 4, 2023 9:00 AM |
Julian Arroyo |
|
Final Disapproved -contractor not ready for final -As of July 2022 All MEP rough-in inspections must be approved proir to the framing inspection |
|
| BUILDING - Spot Check |
Available |
|
|
|
|
|
|
|
| BUILDING - Other |
Available |
|
|
|
|
|
|
|
| BUILDING - Angle |
Available |
|
|
|
|
|
|
|
| BUILDING - Final/Multi-Family |
Available |
|
|
|
|
|
|
|
| BUILDING - Above Ceiling |
Available |
|
|
|
|
|
|
|
| BUILDING - Stocking |
Available |
|
|
|
|
|
|
|
|
Carry-Over |
|
|
|
|
|
|
|
| BUILDING - Final |
Canceled |
Not Applicable |
|
June 16, 2023 10:46 AM |
Shaun Liggett |
|
final canceled - spoke to contractor and owner/applicant regarding required documents for child care facility to be present at final inspection. discussed with owner multiple trade sign offs are required for the CofO for the change in use and they will need there final approvals for all trades including MEP, fireprevention and cross connection. |
|
| BUILDING - Framing |
Failed |
Disapproved |
|
January 19, 2023 10:25 AM |
Julian Arroyo |
|
Framing Disapproved -No access building locked |
|
| BUILDING - Framing |
Failed |
Disapproved |
|
January 23, 2023 10:48 AM |
Shaun Liggett |
|
Framing Disapproved- seal all penetrations thru top plates. contractor on site and had insulated. explained to remove or expose all the plumbing and electrical penetrations and seal so we can observe. also explained to insulate the spaces at all exterior walls door and windows. they are to schedule reinsspect for framing and insulation at same time leave all items exposed. |
|
| BUILDING - Framing |
Failed |
Disapproved |
|
January 25, 2023 12:15 PM |
Julian Arroyo |
|
Framing Disapproved 1 Pull down the insulation at all wire and pipe penetrations and expose for reinspection 2 Spray foam behind the electrical boxes on the exterior walls and leave exposed for reinspection |
|
| BUILDING - Insulation |
Passed |
Approved |
|
January 30, 2023 12:49 PM |
Julian Arroyo |
|
Batt Insulation Approved |
|
| BUILDING - Framing |
Failed |
Disapproved |
100 |
January 26, 2023 10:25 AM |
Julian Arroyo |
|
Framing Disapproved Repeat Items from the previous inspection 1 Pull down the insulation at all wire and pipe penetrations and expose for reinspection 2 Spray foam behind the electrical boxes on the exterior walls and leave exposed for reinspection |
|
| BUILDING - Framing |
Passed |
Approved |
|
January 30, 2023 12:49 PM |
Julian Arroyo |
|
Framing Approved |
|
| BUILDING - Final |
Failed |
Disapproved |
|
July 24, 2023 12:03 PM |
Julian Arroyo |
|
Final Disapproved 1 Door hardware must single action lever handle divise without the pinching turning locking unlocking action |
|
| BUILDING - Final |
Passed |
Approved for Occupancy |
|
August 16, 2023 9:26 AM |
Julian Arroyo |
|
Final Approved -a conditional CO has been issues the Fire Marshall has listed a condition for a Knox Box you may need to contact him when this condition has been met I have filled out the paperwork and left it on the counter top for you |
|