BUILDING - Footing |
Available |
|
|
|
|
|
|
|
BUILDING - Framing |
Passed |
Not Applicable |
|
August 4, 2022 1:18 PM |
Karey McConnell |
|
Framing Approved Above Hard Ceiling Soffit at Front Reception |
|
BUILDING - Slab |
Canceled |
Not Applicable |
|
July 1, 2022 12:00 AM |
Karey McConnell |
|
|
|
BUILDING - Framing |
Passed |
Approved |
|
July 28, 2022 9:14 AM |
Karey McConnell |
|
Framing Partial Approved 2 Hour Fire Wall |
|
BUILDING - Insulation |
Passed |
Approved |
|
August 5, 2022 1:48 PM |
Karey McConnell |
|
Insulation Approved Observed Exterior Walls R-19 Batt in all disturbed cavities. |
|
BUILDING - Final |
Passed |
Approved for Occupancy |
|
October 13, 2022 10:01 AM |
Karey McConnell |
|
Building Final Approved. Note Fire, Mechanical and Cross Connection remain to complete CO sign offs. |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
August 2, 2022 1:09 PM |
Karey McConnell |
|
Approved Layer Inspection for Rated Assembly. Observed each side 5/8. |
|
BUILDING - Insulation |
Passed |
Approved |
|
September 9, 2022 10:11 AM |
Karey McConnell |
|
Insulation Approved X Ray Room Observed R-19 Batt |
|
BUILDING - Angle |
Available |
|
|
|
|
|
|
|
BUILDING - Final/Multi-Family |
Available |
|
|
|
|
|
|
|
BUILDING - Above Ceiling |
Failed |
Disapproved |
|
July 14, 2022 1:27 PM |
Karey McConnell |
|
Note 2 Hour Wall is needed. Please call Inspections Framing and Layer Inspection. Please call me if you have any questions |
|
BUILDING - Stocking |
Available |
|
|
|
|
|
|
|
BUILDING - Slab |
Failed |
Disapproved |
|
July 13, 2022 8:38 AM |
Karey McConnell |
|
Slab Disapproved. Not ready. Moving pipe at large section back. |
|
BUILDING - Slab |
Passed |
Approved |
|
July 14, 2022 1:27 PM |
Karey McConnell |
|
Slab Pour Back Approved Full Inspection |
|
BUILDING - Above Ceiling |
Passed |
Approved |
|
September 2, 2022 9:50 AM |
Steve Crist |
|
Demising wall sealed and marked |
|
BUILDING - Framing |
Canceled |
Not Applicable |
|
August 2, 2022 1:09 PM |
Karey McConnell |
|
Framing Cancelled No Inspection. As of July 2022, ALL trade rough ins must be complete and pass inspection prior to scheduling a framing inspection. As of this date, there are outstanding rough-in inspections to be completed. |
|
BUILDING - Framing |
Passed |
Not Applicable |
|
August 4, 2022 1:18 PM |
Karey McConnell |
|
Framing Partial Approved. All Interior rooms and Exterior build out walls minus The X Ray Room. This will need to be a separate framing inspection. |
|
BUILDING - Framing |
Canceled |
Not Applicable |
|
September 8, 2022 10:05 AM |
Karey McConnell |
|
X Ray Room Framing Cancelled No Inspection. As of July 2022, ALL trade rough ins must be complete and pass inspection prior to scheduling a framing inspection. |
|
BUILDING - Framing |
Passed |
Approved |
|
September 9, 2022 10:11 AM |
Karey McConnell |
|
Framing Approved X Ray Room |
|