BUILDING - Footing |
Available |
|
|
|
|
|
|
|
BUILDING - Foundation |
Available |
|
|
|
|
|
|
|
BUILDING - Slab |
Passed |
Not Applicable |
|
November 28, 2022 11:41 AM |
Shaun Liggett |
|
mono slab -third party letter and design professional inspecton form in box |
|
BUILDING - Framing |
Failed |
Disapproved |
|
November 28, 2022 11:41 AM |
Shaun Liggett |
|
framing inspection disapproved- must have foundation survey uploaded online or in box |
|
BUILDING - Insulation |
Passed |
Approved |
|
December 29, 2022 12:00 AM |
Peter Gervais |
|
Framing has failed - observed batts throughout - double R-19 and regular R-38 in ceiling
|
|
BUILDING - Final |
Failed |
Disapproved |
|
August 3, 2023 12:51 PM |
Todd Miller |
|
1) submit termite treatment certif and fill out and sign EEC - received all other paperwork |
|
BUILDING - Spot Check |
Available |
|
|
|
|
|
|
|
BUILDING - Other |
Available |
|
|
|
|
|
|
|
BUILDING - Angle |
Available |
|
|
|
|
|
|
|
BUILDING - Final/Multi-Family |
Available |
|
|
|
|
|
|
|
BUILDING - Above Ceiling |
Available |
|
|
|
|
|
|
|
BUILDING - Stocking |
Available |
|
|
|
|
|
|
|
BUILDING - Framing |
Failed |
Disapproved |
|
November 29, 2022 1:34 PM |
Steve Crist |
|
1) Missing bolts and nuts throughout 2) Missing hold downs per plan 3) Provide TJI layout 4) Fire block or seal top of pantry walls at dropped ceiling 5) Plan calls for 3 ply LVL over rear bedroom 6) Fire block stair left side 7) Strap wall joints at stair 8) 2nd floor hold downs missing // Do not insulate |
|
BUILDING - Framing |
Failed |
Disapproved |
100 |
December 14, 2022 10:46 AM |
Shaun Liggett |
|
1) Missing bolts and nuts throughout 2) Missing hold downs per plan - no bolts in holdowns 3) Provide TJI layout 4) Fire block or seal top of pantry walls at dropped ceiling // Do not insulate - pay fee before scheduling next inspection |
|
BUILDING - Framing |
Passed |
Approved |
|
December 22, 2022 12:39 PM |
Shaun Liggett |
|
framing approved |
|
BUILDING - Framing |
Failed |
Disapproved |
|
December 29, 2022 12:00 AM |
Peter Gervais |
|
1) Seal fire blocking around AC chase near stairs 2) Fire block and seal knee wall stairs - pictures in workforce
|
|
BUILDING - Framing |
Passed |
Approved |
|
December 30, 2022 12:00 AM |
Peter Gervais |
|
Previous items completed |
|
BUILDING - Final |
Passed |
Approved for Occupancy |
|
August 29, 2023 12:00 AM |
Peter Gervais |
|
City impact and engineering sign-offs still needed for CO - Previous items complete - previous items only |
|