BUILDING - Footing |
Passed |
Not Applicable |
|
February 15, 2023 6:22 AM |
Steve Crist |
|
Approved for 3rd party approval per dept guidlines. |
|
BUILDING - Foundation |
Passed |
Not Applicable |
|
February 15, 2023 6:24 AM |
Steve Crist |
|
Approved for 3rd party approval per dept guidlines. |
|
BUILDING - Slab |
Available |
|
|
|
|
|
|
|
BUILDING - Framing |
Failed |
Disapproved |
|
March 3, 2023 11:23 AM |
Karey McConnell |
|
Framing Disapproved Foundation Survey & 3rd Party Footings Attached. Do not insulate. 1) Missing hold downs at garage door opening. 2) ) With ASTM rated sealant, seal all penetrations, tension bars, top and bottom plates and empty holes. Seal at a break point every 10 foot of any horizontal runs. 3) Shaft wall through out. Repair water damaged areas. Fire seal completely at all 10 foot vertical members. At stair complete through the floors. Fire seal at top, sides and bottom. 4) 3rd floor chase missing fire blocking at top. |
|
BUILDING - Insulation |
Passed |
Approved |
|
March 22, 2023 10:20 AM |
Steve Crist |
|
Walls and ceilings fully batted, doors and windows sealed |
|
BUILDING - Final |
Passed |
Approved for Occupancy |
|
January 11, 2024 9:42 AM |
Karey McConnell |
|
Building Final Approved |
|
BUILDING - Spot Check |
Available |
|
|
|
|
|
|
|
BUILDING - Other |
Available |
|
|
|
|
|
|
|
BUILDING - Angle |
Available |
|
|
|
|
|
|
|
BUILDING - Final/Multi-Family |
Available |
|
|
|
|
|
|
|
BUILDING - Above Ceiling |
Available |
|
|
|
|
|
|
|
BUILDING - Stocking |
Available |
|
|
|
|
|
|
|
BUILDING - Framing |
Failed |
Disapproved |
100 |
March 14, 2023 11:14 AM |
Steve Crist |
|
1) Seal tension rods top and bottom plates all 3 floors 2) Seal fire stopping 3rd floor right wall behind each stud between plwood blocks // fee added // do not insulate |
|
BUILDING - Framing |
Passed |
Approved |
|
March 20, 2023 9:15 AM |
Steve Crist |
|
Corrections completed |
|